Friday, December 29, 2006

• Concrete Swale & Underground Elec Work




Thursday, December 21, 2006

• Concrete Swale Form Work





Monday, December 18, 2006

• Site Prepartion & Earth Work






Soil Compaction and Aggregate Base Compaction were completed.

Tuesday, December 12, 2006

• Demolition of Asphlat & Pulverzation





Monday, December 11, 2006

• Demolitin of Asphlat and Haul Away

Civil Engineer Abraham visited and attended at our Meeting for soil work.




Thursday, December 07, 2006

• Mobilization and Demolition

We have set up the site Office and storage container. Also started to tear down the exisitng building after disconnection of site utilities.


Monday, December 04, 2006

• Ground Breaking Ceremony








Ground Breaking Ceremony was held at 10:00am.
NOCCC, Fullerton College, CW Driver, R2A Architect, &
MTM Construction Inc. and their sub traders were attended at Ceremony.

Saturday, December 02, 2006

• First Day(NTP) of Project, Mobilization started

Installation of Temporary Fence and Site Survey was performed.